At this point I would have to agree with VOXO that it is simply not viable for Equinix (EQ) to put gas in. The reasoning:
1. You have a DATA CENTER in one single floor plan area that houses say 400 cabinets.
2. Gas for the area has to be 1.3 x the volume of the room to be 100% effective (Allowing for leakage ETC). They have extremely high ceilings at EQ so that is one big area to cover.
3. You are already full and very profitable... Why would you bother? Everyone has signed up knowing it was water only. So the Gas function cannot bring you any more money as you are full....
The End
Now... Part 2. If they do not put a Gas System in Stage 2 which is currently under construction then it is clear that it is a monetary based decision on that fact that clients will still just come of the back of the name.